RECOVERY · PROGRESS HELD · 1,555 ACTIVITIES

Six Weeks Back,
and Who Pays for Them

A fourteen-storey tower, six weeks late at month 14. The client wants the date, the QS wants the price, the site manager wants steady gangs, the project manager wants the fewest reissued dates. One programme, four plans, every figure read off the app.

Month 14 on a fourteen-storey tower in Leeds. The frame gang lost ten working days on each of four floors over the winter, and the programme everyone is now working to finishes on 4 May 2027 instead of 18 March: thirty working days, six working weeks. The client wants the date back. The QS wants to know what that costs. The site manager wants a plan the gangs can live with. The project manager wants the fewest reissued dates, inside the window already promised to the subcontractors. Four honest asks; the recovery meeting usually answers one. So I built the tower, slipped it, and asked for all four.

The programme

Hollinwick Quay is a generated scheme: a 14-storey tower over a two-storey podium, 182 flats, £74,000,000 of priced work, 1,555 activities and 2,180 links from 3 February 2025. Ten trades on hourly rates with the gang counts the file declares: nine M&E fitters, seven drylining gangs, five kitchen and bathroom fitters, seven decorators and floor layers, three snagging teams, two frame gangs. Standing costs of £55,000 a week for site management, welfare, security and hoists, added through the app. The developer and the scheme are invented; the shape of the job is not.

The file went in through the welcome page with the option that invents a faster way of working for every activity. I set it to 60% of the duration for 120% of the cost; the app's defaults are 70 and 180, and both are a judgement. Import took seven seconds. The fourteen-point check passed ten of eleven: high float fails, as it should, because read by logic alone 94% of this job could float more than 44 days. Gangs pace a tower, not links. With the dates limited by the gang counts, the board's finish moved from 22 February to 22 March 2027.

The DCMA schedule check that opened on import: gate pass, ten of eleven checks passing, high float failing at 0.936, critical path test passing
The check that opens before the chart does: 10 of 11 pass, three not applicable with nothing started. High float fails at 93.6%, which on a gang-paced tower is the truth, not a fault.
The board's Settings dialog: the ten gangs with the counts the file declares, and dates set to limited by the gang counts above
Settings on the board: the gang counts exactly as the file carries them, and the dates limited by those counts.

A first search on the issued file gave the plan nearest the issued dates: the file's own way of working throughout and a finish of 18 March 2027. That became the baseline, the programme the subcontractors were sent.

Fourteen months later

Floors four to seven of the frame took 28 working days each instead of 18, and everything above and behind them waited. The progress went in through the app's own progress service, not the database: 334 observations at a status date of 31 March 2026, 316 complete, 18 in progress, 1,221 not started. The board's Progress panel reads 24% of the work done against 25% planned by now, and forecasts 7 May 2027 against the plan's 4 May. The board stretches the started floor to its observed pace; the searches price the rest at the plan's rate, so the two differ by three days. The figures below are the searches'.

The board with the Progress panel open: 334 of 334 activities with progress on file, behind, forecast 3 days late, forecast finish 7 May 2027 against a planned 4 May
The slip as recorded. Behind, forecast three days late: 7 May against a planned 4 May 2027. Work done 24%, planned 25%, earned £17,879,181.
The board showing the late programme: 3 February 2025 to 4 May 2027, 821 days, crew-levelled finish 4 May 2027, progress held on 334 activities
The programme everyone is now working to: 821 days, crew-levelled finish 4 May 2027, progress held on 334 activities. Thirty working days past the date that was issued.

One rule sits under every search that follows. Done work stays where it was done, for as long as it took, the way it was done. Started work stays started, and only what is left of it can move. Nothing unstarted may start before the status date. The app pins all 334 before a search begins, and every plan it lists is laid out with them held.

Four people, two guards

The client's goal is the date. The QS's is the all-in cost: direct work, standing costs, and the price of gangs kept on between their jobs. The late programme is £74,000,000 of direct work and £81,025,040 all in. The site manager's is a steady gang profile, which the board counts as gang changes: every gang put on or stood down, day to day, across the job. Lower is steadier, and the late programme has 1,540. The project manager's is distance from the baseline, counted in activities moved and days moved, with two guards: a stability window of 20 working days from the status date in which no issued date may move, and a change budget of 240 moved activities and 1,200 moved days, about a fifth of what is left. A fifth goal, schedule risk, rides along on the wider search; it gets this one line.

The Settings dialog: status date 31 March 2026, day 421 of the programme; stability window 20 working days; a plan may move at most 240 activities and 1,200 days in total
The status date, the window and the budget, in one place: 31 March 2026, 20 working days, 240 activities and 1,200 days. The budget steers one search and is only reported on the other.

Measured against what?

Measured against the dates issued before the slip, the guards do not mean much. The window holds 102 issued dates, and 88 of them are already overtaken: the work in front of them no longer finishes in time, or the gang they need is already drawn. A search against those dates returned 89 plans and none inside the budget. Even the plan that finishes on the same 4 May moves 1,193 activities by 56,921 days, because the slip has already moved almost everything off its issued day. Against last year's dates the project manager's goal and the client's are the same goal: back to the issued programme.

The board's Recovery panel against the pre-slip baseline: 102 issued dates fall in the stability window, 88 of those already overtaken by the slip; 0 of 89 plans on show are inside the change budget
Against the pre-slip dates: 102 held, 88 overtaken and free to move, and 0 of 89 plans inside the budget.

So the plan of record was switched. The late programme, as the app's own scheduler lays it out with the done work held, became the baseline, with the same window and budget against it. Now 90 issued dates sit in the window, none overtaken, and doing nothing moves nothing. That is the argument the four people are actually having: not distance from last year's dates, but change against the programme everyone is working to today.

The Recovery panel against the late programme: baseline captured from the late programme, 90 issued dates in the stability window, none overtaken, budget of 240 activities and 1,200 days
The same window against the late programme: 90 held, none overtaken.

Two searches, five minutes each

The board's Recovery panel runs two searches over everything not yet finished, on the same time box so their plans can be compared. I gave each five minutes. The first weighs all five goals and reports the budget without obeying it: 158 plans in 153 rounds, from 29 December 2026 to doing nothing, and only doing nothing is inside the budget. Every plan that recovers time moves between 774 and 1,108 open activities, because pulling time back re-orders the flats among the gangs. The second weighs date, cost and closeness to the baseline and is steered by the budget: 47 plans, all 47 inside it, in 178 rounds, nothing earlier than 8 April 2027. Steered to small changes, it cannot reach the old date. The wider search can, and says what that costs.

The plan list of the search on every goal: 5 minutes and 153 rounds, 158 plans, with finish, direct cost, all-in cost, gang changes and moves from the baseline for each
Every goal: 158 plans in five minutes, 153 rounds. The fastest finishes 29 December 2026 for £88,785,304 all in. The line under the heading says which goals the search weighed.
The Recovery panel with the every-goal search on show: 1 of 158 plans on show is inside the change budget
Reported, not enforced: 1 of 158 inside the budget, and that one is doing nothing.
The plan list of the search close to the baseline: 5 minutes and 178 rounds, 47 plans, every one in budget, the fastest finishing 8 April 2027
Close to the baseline: 47 plans in five minutes, 178 rounds, every one inside the budget and every one cheaper all in than doing nothing. Nothing earlier than 8 April 2027.

Back is working days recovered against 4 May 2027; the slip is 30. Cost is all in, with its change against the late programme's £81,025,040. Moved is open activities on a different day, and the days they moved by. The first three plans are from the search close to the baseline, the last two from the search on every goal.

Plan Finish Back All-in cost Moved Faster modes Gang changes
Doing nothing4 May 20270£81,025,0400 / 001,540
The fewest dates moved23 Apr 20276£80,965,596 (−£59,444)36 / 11231,538
The cheapest15 Apr 202712£80,923,588 (−£101,452)156 / 56141,550
The one most could sign8 Apr 202717£80,949,280 (−£75,760)171 / 47461,538
The steadiest gangs23 Apr 20276£81,014,696 (−£10,344)1,010 / 15,67291,438
All six weeks18 Mar 202730£82,152,248 (+£1,127,208)970 / 8,9431691,572
The plan row for the fewest dates moved: 23 April 2027, 11 days faster, direct cost £54,100 more, all-in £80,965,596, save £59,444, 1,538 gang changes, 36 activities and 112 days moved, in budget
The fewest dates moved. Six working days back, 36 activities on a new day, £54,100 more of direct work and £59,444 less all in. Three invented ways of working.
The plan row for the cheapest plan: 15 April 2027, 19 days faster, direct cost £70,700 more, all-in £80,923,588, save £101,452, 1,550 gang changes, 156 activities and 561 days moved, in budget
The cheapest. Twelve days back for £101,452 less all in: fewer weeks of standing cost, and gangs kept on for less idle time. 156 activities move.
The plan row for the one most could sign: 8 April 2027, 26 days faster, direct cost £146,760 more, all-in £80,949,280, save £75,760, 1,538 gang changes, 171 activities and 474 days moved, in budget
The one most could sign. Seventeen days back, 171 activities and 474 days of movement, still inside the budget, six invented ways of working, £75,760 saved, and two fewer gang changes than doing nothing.
The plan row for the steadiest gangs: 23 April 2027, 11 days faster, all-in £81,014,696, save £10,344, 1,438 gang changes, 102 fewer, 1,010 activities and 15,672 days moved, over budget
The steadiest gangs. 1,438 gang changes, 102 fewer than doing nothing, six days back and £10,344 saved. It re-dates 1,010 activities to do it.
The plan row for the full recovery: 18 March 2027, 47 days faster, direct cost £1,534,880 more with 169 invented modes, all-in £82,152,248, £1,127,208 more, 1,572 gang changes, 970 activities and 8,943 days moved, over budget
All six weeks. 18 March 2027, the date that was issued, for £1,127,208 more than doing nothing all in: £1,534,880 of extra direct work, less the standing costs of the 47 days it wins back. 169 activities on their faster way of working, 970 open activities re-dated.
The board with the full-recovery plan loaded: 3 February 2025 to 18 March 2027, 774 days, direct cost £75,534,880, progress held on 334 activities
The same plan loaded on the board, done work still held: 774 days, 18 March 2027, £75,534,880 of direct work.
The Recovery panel's gangs and plant list for the full recovery: ten gangs, none with a clash day; M&E fitters peak at 9 of 9, decorators 7 of 7, kitchen fitters 5 of 5
What the six weeks ask of the gangs: M&E at 9 of 9, decorators 7 of 7, kitchens 5 of 5, and no clash day on any of the ten gangs. The time comes from the invented modes, not from gangs that do not exist.

The price of time

The first weeks back cost nothing. Every one of the 47 plans close to the baseline is cheaper all in than doing nothing, by £49,300 to £101,452, and so are 27 of the wider search's 158: fewer weeks of standing cost pay for the few faster ways of working they use. Beyond 8 April only the wider search has plans, and the price climbs: 20 working days back for £301,544 more, 22 for £720,096, 29 for £1,118,832, and the full 30 to the original 18 March for £1,127,208. It is not a perfectly smooth curve; the plan to 9 April costs more than the one to 5 April. Past the old date the slope is steep: 35 days back costs £1,344,724, and the fastest plan on the list, 29 December 2026, costs £7,760,264 more and leans on 1,008 invented ways of working. That is the answer to the QS, and it is an all-in answer: the direct cost of the six weeks is £1,534,880, and £407,672 of it comes back in standing costs and idle gangs.

What the site manager's goal was worth

Both searches had the same five minutes, so this is like for like. The search close to the baseline does not weigh gang changes at all, and its 47 plans sit between 1,534 and 1,556: within sixteen of doing nothing either way. The search that does weigh them found plans from 1,438 to 1,648. Its steadiest, at 23 April, has 102 fewer gang changes than doing nothing and costs £10,344 less, and it moves 1,010 activities to get there. The plan with the fewest moved dates finishes on the same 23 April with 1,538 gang changes and 36 activities moved. So the site manager's goal is worth about a hundred gang changes on this job, and the project manager pays for all of them. Where both searches reach the same date, the narrow one is cheaper: to 9 April it saves £93,020 and moves 196 activities, where the wider search's cheapest plan to that date costs £385,108 more, moves 849 and has 1,642 gang changes. The wider search earns its place at the ends: the steadier plans in late April, and every date before 8 April.

What would it take?

The board's Optimize panel after chasing a finish of 23 March 2027: 8 of 8 plans hit it, each listed with days faster, window cost and invented modes used
The board's own thirty-second search, told to chase 23 March 2027: 8 of 8 plans hit it, the dearest 134 days faster for £9.78m more and 1,050 invented modes.

The board's "What would it take?" button only appears when the ways of working cannot reach a date, and its answer is extra crews. Here they can, so it never showed. The honest answer on this programme is the wider search's: the date is reachable, and the question is who pays the £1.13m. The thirty-second plans are dearer because that search is short and weighs direct cost alone.

Two of this article's results were fixes to the app itself: until this week the search would re-plan completed work, and the stability window would hold an issued date even when the work before it could no longer finish in time or the gang was already drawn. Both are fixed, and every figure above is from after the fix.

What this does not tell you

The faster ways of working are invented, 60% of the time for 120% of the cost, and a subcontractor can refuse any of them; the six-weeks plan leans on 169. The window and the budget are judgement calls, and the narrow search's menu moves when they do. Done work was held at the plan's rate, so the searches and the board's forecast disagree by three days. The tower crane is not modelled. Each search had five minutes; a longer one may find better, and a different run will not return the same list. Underneath the two searches is a many-goal search; the article did not need its name.

Run it on your own slip

GeneraGantt reads MS Project, Primavera P6 and Asta Powerproject. Record the progress, set the baseline everyone is actually working to, set the window you have promised and the budget you can defend, and run both searches. Take the menu to the meeting instead of one plan. Free while it is in testing, with a sample programme loaded. Nothing is saved: your schedule leaves with you.

The programme is a generated one, built so that a frame slip lands where it would on a real tower: on the floors, then on every trade behind them. Every figure is read off the app after importing the file, recording the progress through the app's own service and running the searches from the board; nothing is quoted that was not read off its screens.